Ambridge Area School District

901 Duss Avenue, Ambridge PA 15003 | 724.266.2833

  
  

who student 150who staff 150who parents 150

Junior High School

401 First Street, Freedom, PA 15042 | 724.266.2833 | f. 724-869-5321
Principal, Mr. Shaun Cooke x3245

New jh1New jh2New jh3

Top Left: Conference of Administration Area

Top Right: New Split System Installed in the Testing

Bottom: Mechanical Room Nearing 90% Completion

vent hew power

- New Unit Ventilator, Book Cases and piping covers installed.
- New High Efficiency Hot water Heating system is online today for start of school.
- 3000 Amp Load Center 95% Installed and operational.

 

Installations under way
• The Piping mains in the hallways are about 98 percent installed and have been pressure tested. Ceiling tiles are being reinstalled.
• All of the classroom and Hallway Unit Ventilators and Shelving Units are received and are being Installed in their intended locations.
• The pads have been poured in the mechanical Room and the Major equipment and pumps have been set on them.
• The Chiller Pad is constructed.
• The two Air Handling Units in that supply the locker rooms are demolished and the replacements are hung in place.
• Ductwork and Piping is being installed on the ceiling mounted Unit Ventilators .
• Hydronic Final Connections are being installed on the RTUs
• The Roofing is finished and the RTUs are set in place.
• Piping run outs have been started and are 95% Complete- Insulation is following very closely to piping completions.
• Electrical circuits are being installed.
• Mini Cassette Evaporator hung in Shop and Faculty area.
• DLC has been on site for first shutdown and is sending an engineer to access the vault condition (Pending).
• Switch Gear is in schedule and will arrive by Monday 8/15/16 (Did not arrive and is being investigated)
• Installation of Boilers, HW Heaters, Pumps and other Hydronic have continue and are around 45 % installed.
• OZ Enterprises continues with their wiring trunk installation

Read more: Ambridge Area Junior High School HVAC Update 8/26/16

abc

Pictures of Renick Sheet Metal Foreman Rob Dunbar whom resides in Freedom Pa. Pictures capture the care taken to prevent dirt from entering the duct after production in Butler Pa and as its stored on the project site. The procedure of covering duct in this fashion is used in Leeds Certified projects.

 

Installations under way

• The Piping mains in the hallways are about 98 percent installed and have been pressure tested.
• All of the classroom Unit Ventilators and Shelving Units have been demolished.
• The pads have been poured in the mechanical Room and the Major equipment and pumps have been set on them.
• The Chiller Pad is constructed.
• The two Air Handling Units in that supply the locker rooms are demolished and the replacements are hung in place.
• Ductwork and Piping are being installed on in the Mezzanine and is 90 % complete.
• The Roofing is finished and the RTUs are set in place.
• Piping run outs have been started and are 90% Complete- Insulation is following very closely to piping completions.
• Electrical circuits are being installed.
• Mini Cassette Evaporator hung in Shop and Faculty area.
• DLC has been on site for first shutdown and is sending an engineer to access the vault condition.
• Switch Gear is in schedule and will arrive by Monday 8/15/16
• Unit Ventilators began arriving a today. All will be received by next week. Installations of UVs beginning immediately.
• Installation of Boilers, HW Heaters, Pumps and other Hydronic have started and are around 40 % installed.
• OZ Enterprises have begun installing the Controls wiring.

Read more: Ambridge Area Junior High School HVAC Update 8/10/16

Constellation Energy and Local HVAC Contractor Renick Brothers Set New Roof Top Heating and Cooling equipment as part of  the Ambridge Junior High School Energy Performance  Project currently under construction.

 

Installations under way:

• The Piping mains in the hallways are about 80 percent installed. Insulation of these lines began last week and the majority have been pressure tested.

• All of the classroom Unit Ventilators and Shelving Units have been demolished.

• Boiler Room demolition is around 100%complete and Pads are being poured for Boilers.

• The Chiller Pad is being installed

• The two Air Handling Units in that supply the locker rooms are demolished and the replacements are hung in place.

• Ductwork is being installed on in the Mezzanine.

• The Roofing is finished and the RTUs are set in place.

• Piping run outs have been started and are 20% (no insulation).

• Electrical circuits are being installed.

• Mini Cassette Evaporator hung in Shop.

Read more: Ambridge Area Junior High School HVAC Project Update